Home / Projects / Heavy Industrial & Mining / Sub-Zero Mega Span: Four 151m Bolted Space Frame Coal Sheds Conquering Russian Far East Conditions

Sub-Zero Mega Span: Four 151m Bolted Space Frame Coal Sheds Conquering Russian Far East Conditions

Advanced 3D non-linear modeling accounts for extreme unbalanced snow drifts and wind suction, coupled with calculated reverse camber to ensure zero excessive deflection under 3.0 kPa snow pressure.

PROJECT OVERVIEW

Project Overview

Located at a strategic coal export and logistics terminal in the Russian Far East, this project was launched to comply with strict federal environmental dust-control mandates and expand transshipment capacity. The EPC contractor faced the formidable task of erecting four gigantic enclosed coal sheds (each 151m span × 277m length) before the deep winter freeze set in.

Under extreme conditions of -40°C combined with gale-force winds and blizzards, traditional high-altitude site welding was virtually impossible due to severe cold-cracking risks in the heat-affected zone and prohibitively complex preheating procedures. Moreover, the massive 151m column-free clear span had to sustain heavy Russian design snow loads (SP 20.13330, Snow Zone V reaching 3.0 kPa) as well as unbalanced snow drifting, posing serious structural deflection challenges.

Shijie Heavy Industry delivered an EAC/GOST-compliant, CNC-machined bolted ball-joint space frame system utilizing 09G2S / Q355E low-temperature high-impact structural steel. This achieved 100% mechanical bolt-together assembly on-site, entirely eliminating cryogenic welding hazards. Combined with high-precision camber engineering and thermal-sliding bearings, Shijie empowered the contractor to utilize ground pre-assembly with synchronized hydraulic jacking, breaking erection records in the frozen wilderness.

PROJECT DATA
LocationRussian Far East Coal Logistics Terminal
IndustryBulk Coal Export & Port Logistics Infrastructure
Unit Scale151m (Clear Span) × 277m (Length) × 48m (Apex Height)
Total Area4 Sheds, Totaling ~167,000 sqm
StructureCylindrical Double-Layer Space Frame (Bolted Ball-Joint)
Design CodesSP 16.13330 (Steel Structures), SP 20.13330 (Loads & Actions)
Design Loads-45°C extreme temp; 3.0 kPa snow load (Zone V)
Steel Grade09G2S-12 / Q355E (-40°C Charpy V-Notch impact tested)
Site Welding0% (100% factory CNC machined bolted connections)
Hoisting PlanBlock ground pre-assembly & synchronized hydraulic jacking
01

Mega-Span & Extreme Snow Resistance (SP 20.13330 Compliance)

Advanced 3D non-linear modeling accounts for extreme unbalanced snow drifts and wind suction, coupled with calculated reverse camber to ensure zero excessive deflection under 3.0 kPa snow pressure.

02

Zero-Welding Cryogenic Assembly

100% high-precision CNC-machined bolted ball joints completely avoid the fatal risk of cold brittleness and weld cracking in sub-zero Siberian/Far East conditions.

03

09G2S Cryogenic High-Strength Steel

Utilizing 09G2S (equivalent to Q355E) with certified Charpy V-notch impact toughness tested at -40°C, ensuring high structural ductility and zero brittle fracture risk.

04

Multi-Directional Thermal Sliding Joints

Engineered sliding bearings absorb excessive expansion and contraction caused by annual 70°C temperature shifts, safely releasing lateral forces on retaining concrete walls.

Turning Site Challenges into Engineered Certainty

Proven technical interventions to keep your project on spec, on budget, and on schedule

THE CHALLENGE

Massive 151m span subjected to severe seasonal temperature swings (from -40°C in winter to +30°C in summer), generating extreme thermal expansion/contraction stresses.

SJ ENGINEERED SOLUTION

Integrated low-friction spherical sliding bearings with ± 60mm displacement tolerance, allowing micro horizontal sliding to safely isolate and release thermal stress.

THE CHALLENGE

Extreme heavy snow drifting (up to 3.0 kPa) on curved roofs causing asymmetric localized overloading and buckling hazards.

SJ ENGINEERED SOLUTION

Reinforced critical chord and web member profiles along snow-accumulation zones based on SP 20 Annex G algorithms, combined with snow-retaining guides at eaves to prevent sudden ice avalanches.

THE CHALLENGE

Sorting tens of thousands of structural components on an open job site covered by thick snow and frost, threatening construction schedules.

SJ ENGINEERED SOLUTION

Applied deep-etched laser barcodes and cryogenic QR labels onto each component; pre-sorted and packaged parts by hydraulic jacking modules for direct scanned identification.

Alexey V.
CLIENT VOICE

Any structural engineer will confirm that a 151-meter clear span pushes the outer edge of space-frame engineering. Executing four of them back-to-back under the punishing conditions of the Russian Far East—facing -40°C chills and stringent snow load requirements under SP 20—felt like high-stakes gambling. Our primary concern was site welding; executing reliable high-altitude structural welds in severe freezing conditions is practically impossible and technically unsafe.

Shijie Heavy Industry proved to be the decisive partner for this project. They supplied an EAC-certified, CNC-machined bolted ball-joint system manufactured from cold-tough 09G2S steel that completely replaced field welding with high-torque mechanical bolting. The fabrication tolerance was kept within 1.0 mm, which was incredible. My team assembled the large frame sections on the ground and hoisted them with synchronized hydraulic jacks without a single node binding. Their sliding bearing design completely dissipated the thermal contraction of the 151-meter structure. Shijie delivered world-class heavy steel engineering that conquered one of the harshest winters in port construction history.

Alexey V.
EPC General Contractor Director (Far East Port Projects)

Products Used in Project

Similar Projects

To be confirmed

Why Global Contractors Choose SynJect

Predictable delivery, certified compliance, and direct engineering support for zero-risk execution

Delivery

Pre-assembled in our factory and 3D-nested for containers to cut ocean freight and site delays

Compliance

Fabricated strictly to CE EN 1090-1, AISC, and ISO 9001 / 14001 / 45001 with full NDT traceability

Team

Work directly with senior structural engineers from Tekla 3D modeling to on-site erection

Frequently Asked Questions

To be confirmed

To be confirmed

To be confirmed

To be confirmed

Get Your 24-Hour BOQ and Cost Plan

See how much steel tonnage and ocean freight you can save before fabrication begins

8–15%

Steel Weight Savings

1:1 Tekla 3D modeling optimizes beam-column ratios to eliminate redundant material costs.

0.0mm

Zero-Clash Code Verification

Checked against EN 1090 and local wind/seismic loads.

100%

Engineer-to-Engineer Review

Verified by our lead engineers—Zero pushy sales calls, Just actionable data and factory price.

CE EN 1090-1•ISO 9001•ISO 14001•ISO 45001

Engineering & Inquiry Desk

Lead Engineers Online

Drawings
Drawings

🔒 100% Private and Secure, No Spam